Vol. 18 Number 20

Vancouver Island, British Columbia  Wednesday, October 20, 2004

$1.25 includes GST

Ian Redden,Darrell Bergen, Paul Johnson, Eddie Mark and Wayne Hinchecliffe pause for a photo while olanting trees in the river bottom.

Miriam Trevis
The Record
 

Quietly and unobtrusively, Mother Nature is being given a helping hand in the Elk River valley near Gold River.

The river, once a favourite fly-fishing venue for Roderick Haig-Brown, has suffered many indignities over the past 50 years. As a result, serious degradation has occurred along the banks which has allowed the river to meander from its original course to become a delta of small streams varying their channels over the large gravel flood plain as the river enters Upper Campbell Lake.

As part of its Bridge Coastal Fish and Wildlife Restoration Program, BC Hydro agreed to sponsor restoration work on the Elk River when it was proposed and the work has been overseen by Ian Redden, a biologist working for Streamline Environmental Consulting out of Nanaimo. Redden told The Record that over the past half-century, the river has been impacted by many natural events and man-made projects. These include the massive landslide which resulted from an earthquake in 1946 which created Landslide Lake where the river rises. The landslide sent sediment into the upper channel of the river. In the 1940's the entire valley bottom was logged and then further diversions ensued with the construction of Highway 28, the Elk River Timber road and Strathcona Dam.

Roger Dunlop, marine biologist with [he Nuu-chah-nulth Tribal Council stated that when the Mowachaht/Muchalaht First Nations entered into discussions

with BC Hydro regarding the removal of the Heber Dam and penstock (pipeline) which diverts the Heber River eastward, all the rivers in the area were part of the debate. Some thought was given to putting the original block back at the end of Mud Lake which was opened up when the pipeline went in. It was decided, however, that considerable work would then have to be done to Highway 28 as the resulting water levels in Crest and Mud Lakes would create flooding if the roadbed was not elevated sufficiently.

Thoughts then turned to restoration of the Elk River which is one of the major spawning channels for rainbow and cutthroat trout, together with Doily Varden resident in Upper Campbell and Buttle Lakes.

The silviculture crew from the Mowachaht/Muchalaht First Nations were hired to do the work which started in September and has now finished for this season. The object is to build up the gravel bars to push the river back towards its original course. Four-foot lengths of dogwood and willows are collected and soaked in the river for a week, thus ridding them of hormones . which inhibit rooting. At 20,000 stems per hectare, the work is time consuming as the first three feet of the stems is pushed into the gravel bar after an excavator has removed the top layer of gravel. The stems need to be put in that deeply to ensure that the newly rooted shoots will not be impacted by a drop in me water table.

As the plants become established, debris will be trapped which will allow

the gravel bars to build up, forcing the river to go round rather than over them. As nature takes its course, other vegetation will grow naturally on the raised gravel bars as re-forestation gradually takes place.

The whole project has received tremendous support from the community of Gold River according to Redden. Students from the High School, involved with the Gold River Streamkeepers Society have volun-

teered time at the site (including a Pro-D day) and the work done by the members of the Mowachaht/Muchalaht First Nations has been first class.

Everyone involved with the project is hopeful that this is just Phase One. While no commitment of additional funding has yet been given by BC Hydro, the groups who have worked hard on this initial phase are hopeful that its success will encourage further investment from Hydro.


Ian Redden with replanted bar in foreground